MUJI 2d CV2239

Impossibility.

activein force · 2026-08-21 – presentas-observed

[Name of contractor] claims that [he] is excused from performing the contract because [insert description of circumstances] made the main purpose of the contract impossible to perform. To succeed on this claim, [name of contractor] must prove that:

(1) the main purpose of the contract is no longer possible;

(2) [name of contractor] did not create the events that made the main purpose impossible, and they were beyond [his] control; and

(3) the events that made the main purpose impossible were not reasonably foreseeable by either party at the time the contract was made.

Provenance

Source
legacy.utcourts.gov
Retrieved
2026-08-22
Edition
2026-08-21
Content hash
50f177be31849432ee29e4a73375beac00c8df03d0a297d0715183c1e385b178
View the official source →

The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.

Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.

Coverage · API docs

Bindinglaw

Point-in-time US law with the receipt attached. Source URL, retrieval time, content hash, and validity dates on every answer.

curl api.binding.law/v1/law/coverage

© 2026 binding.law · a Jubal, Inc. productAttorneys and firms never pay. Ever.
MUJI 2d CV2239 — Impossibility. · binding.law