MUJI 2d CV2239
Impossibility.
[Name of contractor] claims that [he] is excused from performing the contract because [insert description of circumstances] made the main purpose of the contract impossible to perform. To succeed on this claim, [name of contractor] must prove that:
(1) the main purpose of the contract is no longer possible;
(2) [name of contractor] did not create the events that made the main purpose impossible, and they were beyond [his] control; and
(3) the events that made the main purpose impossible were not reasonably foreseeable by either party at the time the contract was made.
Provenance
- Source
- legacy.utcourts.gov
- Retrieved
- 2026-08-22
- Edition
- 2026-08-21
- Content hash
50f177be31849432ee29e4a73375beac00c8df03d0a297d0715183c1e385b178
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.