MUJI 2d CV2237
Liquidated damages.
[Name of owner] seeks to recover the damages stated in the contract for failing to complete the project on time. You must award the damages stated in the contract if you find that, at the time the parties entered into the contract:
(1) the agreed-upon damages was a reasonable forecast of the damages [name of owner] would suffer as a result of a delay, and
(2) the actual damages that would arise from the delay were difficult to estimate accurately.
Provenance
- Source
- legacy.utcourts.gov
- Retrieved
- 2026-08-22
- Edition
- 2026-08-21
- Content hash
95c916d3b989cc4c97637f14f947d1268d42e8a80cf05b8f1f287cf19253930d
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.