MUJI 2d CV2227

Right to suspend work due to non-payment.

activein force · 2026-08-21 – presentas-observed

[Name of contractor] claims [he] suspended the work because of non-payment. To succeed on this claim, [name of contractor] must prove that:

(1) [name of owner] failed to make required progress payment(s);

(2) [name of owner]'s failure to make the payment(s) was an important breach of the contract; and

(3) [name of owner] had no reasonable excuse to withhold the payment(s).

Provenance

Source
legacy.utcourts.gov
Retrieved
2026-08-22
Edition
2026-08-21
Content hash
26df47b84fc906928f466069f1b14ae2d964ef5d9b44674df4e30cee174c4058
View the official source →

The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.

Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.

Coverage · API docs

Bindinglaw

Point-in-time US law with the receipt attached. Source URL, retrieval time, content hash, and validity dates on every answer.

curl api.binding.law/v1/law/coverage

© 2026 binding.law · a Jubal, Inc. productAttorneys and firms never pay. Ever.