Contractor's claim for time. Delay not caused by the contractor.

activein force · 2026-08-21 – presentas-observed

[Name of contractor] claims [he] was entitled to more time to perform the work because of an excusable delay. To succeed on this claim, [name of contractor] must prove that the events causing the delay:

(1) were beyond [name of contractor]'s control;

(2) were not reasonably foreseeable by [name of contractor] at the time the contract was made; and

(3) prevented [name of contractor] from meeting the contract deadline.

Provenance

Source
legacy.utcourts.gov
Retrieved
2026-08-22
Edition
2026-08-21
Content hash
54adb66c538046a8d717c71f0ce5eb50539a00b1d6f816f19e1a0851df4b844e
View the official source →

The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.

Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.

Coverage · API docs

Bindinglaw

Point-in-time US law with the receipt attached. Source URL, retrieval time, content hash, and validity dates on every answer.

curl api.binding.law/v1/law/coverage

© 2026 binding.law · a Jubal, Inc. productAttorneys and firms never pay. Ever.