MUJI 2d CV2218

Claim for extra work due to site conditions different from contract terms (Type 1 differing site condition).

activein force · 2026-08-21 – presentas-observed

[Name of contractor] claims additional [time/compensation] for extra work caused by actual site conditions different from those described in the contract documents. To succeed on this claim, [name of contractor] must prove that:

(1) the contract documents describe certain site conditions;

(2) [name of contractor] reasonably relied on the description;

(3) [the actual site conditions were different from those described; and

(4) the different site conditions added to [name of contractor]'s [time/costs].

Provenance

Source
legacy.utcourts.gov
Retrieved
2026-08-22
Edition
2026-08-21
Content hash
8fcef8017efcf6cd97efe3c419d1b928f404d34d6f68390f834b270828528404
View the official source →

The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.

Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.

Coverage · API docs

Bindinglaw

Point-in-time US law with the receipt attached. Source URL, retrieval time, content hash, and validity dates on every answer.

curl api.binding.law/v1/law/coverage

© 2026 binding.law · a Jubal, Inc. productAttorneys and firms never pay. Ever.
MUJI 2d CV2218 — Claim for extra work due to site con… · binding.law