UT · jury_instructions
MUJI 2d CV2214
Claim for extra work.
[Name of contractor] claims additional [time/compensation] for work that [name of owner] required but that was not part of the original contract. To succeed on this claim, [name of contractor] must prove that:
(1) the work was not in the parties' original contract;
(2) [name of owner], by words or conduct, directed [name of contractor] to perform the work;
(3) [name of owner] knew or should have known that the work required additional [time/compensation];
(4) [name of contractor] performed the work; and
(5) the work added to [name of contractor]'s [time/costs].
Provenance
- Source
- legacy.utcourts.gov
- Retrieved
- 2026-08-22
- Edition
- 2026-08-21
- Content hash
293a2f9d44e665dae53b1f04567965ea19fbdefba017acaa7f9ceb1677294e9b
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.