Claim for additional costs/time due to denial of access to worksite.

activein force · 2026-08-21 – presentas-observed

[Name of contractor] claims [he] had additional costs and/or was delayed because [name of owner] failed to provide access to the worksite. To succeed on this claim, [name of contractor] must prove that:

(1) [he] was prepared to work on [dates];

(2) [his] failure to perform the work was exclusively because [name of owner] failed to [describe denial of access]; and

(3) [he] had additional costs and/or was delayed.

Provenance

Source
legacy.utcourts.gov
Retrieved
2026-08-22
Edition
2026-08-21
Content hash
d970b4afc586e181125d64628c9e3839a2a7c551eb92f85c83f40bf250b41e17
View the official source →

The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.

Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.

Coverage · API docs

Bindinglaw

Point-in-time US law with the receipt attached. Source URL, retrieval time, content hash, and validity dates on every answer.

curl api.binding.law/v1/law/coverage

© 2026 binding.law · a Jubal, Inc. productAttorneys and firms never pay. Ever.