MUJI 2d CV2206
Owner's duty to inform.
[Name of contractor] claims that [name of owner] had a duty to disclose the following information before the bid was submitted: [describe information.] You must decide whether, [name of contractor] has proved that:
(1) [name of owner] did not disclose the above-described information to [name of contractor];
(2) the undisclosed information was important to [name of contractor]'s ability to perform the contract; and
(3) [name of owner] had knowledge about the undisclosed information that was not available to [name of contractor].
If you find that [name of contractor] has proved all of these facts, then [name of owner] is liable to [name of contractor] for damages.
Provenance
- Source
- legacy.utcourts.gov
- Retrieved
- 2026-08-22
- Edition
- 2026-08-21
- Content hash
7d6b30239989580097590a45b8355d9d2108dcfc976970ad024ee0560bd8a4ae
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.