US · guidance
CMS SOM App. A, Tag A-0806
§482.43(a)(1) Standard: Discharge Planning Process
(1) Any discharge planning evaluation must be made in a timely basis to ensure the
appropriate arrangements for post-hospital care will be made before discharge and to avoid
unnecessary delays in discharge.
Interpretive Guidelines §482.43(a)(1)
After a patient has been identified as needing a discharge planning evaluation, or after a request
for an evaluation has been made by the physician, patient and/or patient’s representative, the
evaluation must be completed timely. This means there must be sufficient time after completion
to allow arrangements for post-hospital care to be made, without having to delay the patient’s
discharge in order to do so, and without unnecessarily transferring the patient to a different
setting than that from which he/she was admitted primarily due to the delay in making
appropriate arrangements. Acute care hospital inpatients frequently have short lengths of stay,
which necessitates prompt attention to patients’ discharge planning needs in acute care
hospitals. Failure to complete the evaluation in a timely manner could make it more difficult to
implement the patient’s final discharge plan, and/or may cause an unnecessary delay in the
patient’s discharge from the hospital.
There may be citations if the hospital does not identify patients likely to need discharge planning
at least 48 hours in advance of the patient’s discharge, and there is evidence that: (1) the
patient’s discharge was delayed due to the hospital’s failure to complete an appropriate
discharge planning evaluation on a timely basis; or (2) that the patient was placed unnecessarily
in a setting other than that from which he/she was admitted primarily due to a delay in discharge
planning. For example, a delay in identification of a patient in need of discharge planning might
result in discharging the patient to a nursing facility, because such placements can be arranged
comparatively quickly, when the patient preferred to return home, and could have been
supported in the home environment with the arrangement of appropriate community services.
If the patient’s stay is for less than 48 hours, hospitals must nevertheless ensure that they are
screened so that, if needed, the discharge planning process is completed before the patient’s
discharge.
For patients that may not have been initially identified as in need of a discharge plan, there may
be changes in the patient’s condition that warrant development of a discharge plan. The
hospital’s discharge planning policies and procedures must address how the staff responsible for
discharge planning will be made aware of changes in a patient’s condition that require a
discharge planning evaluation.
Survey Procedures §482.43(a)(1)
• Identify the hospital’s discharge planning policies and procedures.
• Verify that patients are screened so that the discharge planning process is completed before
the patient’s discharge.
History
Rev. 238; Issued: 03-20-26; Effective: 09-05-25; Implantation: 09-05-25
Provenance
- Source
- cms.gov
- Retrieved
- 2026-07-22
- Edition
- som-2026-07-22
- Content hash
55aacc9229e5ffb953fd6d095ff7ae93fc391f9e342bdca2e69fc9edee74f5e1
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.