The Factory Manager will develop production plans that are consistent with the required delivery
dates of customer orders and demonstrated factory capacities. These plans are reviewed monthly
at the Operations Review Meeting, attended by the:
■ AW/SOI (where applicable).
■ Factory Manager.
■ Business Manager or Operational Accountant.
■ Quality Assurance Manager.
■ Procurement Agent/Contracting Officer (where applicable).
Attendees assess the status of current operations and identify potential constraints that may
prevent the production plan from being achieved successfully.
The Factory Manager identifies any areas for which required capacity is greater than
demonstrated capacity and develops plans to address the capacity shortage through:
■ Production order rescheduling.
■ Hiring additional inmates.
■ Overtime, as approved by the general manager.
■ Other appropriate means.
If customer orders become overloaded to the extent that viable production plans, consistent with
customer order delivery requirements, cannot be established, the AW/SOI confers with the
Program Manager and the CSC and submits a written recovery plan to the General Manager that
analyzes the overloaded condition’s causes and identifies steps to prevent recurrence.
History
PS 8340.10 dated 2015-06-18
Provenance
- Source
- bop.gov
- Retrieved
- 2026-09-20
- Edition
- bop-ps-2026-09-20
- Content hash
4946aca80c3354b60230f65c7eecb1ffaa99868f8bd8cf43eea45915699a04aa
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.