RESPONSIBILITIES
a. The Associate Warden, Industries and Education (AW) or Superintendent of Industries
(SOI)(or Factory Manager for locations without an AW or SOI) will:
■ Ensure that production schedules are consistent with production capacity and order delivery
dates, allowing sufficient shipping lead time.
■ Ensure that the MRP module is used to plan and order materials.
b. The Factory Manager will:
■ Monitor incoming customer orders to ensure delivery dates are realistic and achievable and
notify the Customer Service Center (CSC) within three working days if a delivery date
cannot be met.
■ Develop production plans to meet the required delivery dates of accepted customer orders.
■ Ensure sufficient material availability by generating purchase requests for raw materials
based upon recommendations of MRP Order Action Reports.
■ Use Millennium picklists to requisition materials and work center dispatch lists to plan work
center production.
■ Monitor daily operations and the MRP Exception Report to ensure the production schedule is
maintained.
P8340.10 06/18/2015 2
■ Approve any changes to the production schedule.
At the AW/SOI’s discretion, many of the Factory Manager’s responsibilities may be delegated to
the Production Controller or the person responsible for production scheduling if the location is
staffed accordingly.
History
PS 8340.10 dated 2015-06-18
Provenance
- Source
- bop.gov
- Retrieved
- 2026-09-20
- Edition
- bop-ps-2026-09-20
- Content hash
e15d5c1cd9cabfe4dd191cd18e963b93451601f7417dbc5234e540eaa5e6e1c6
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.