PROGRAM OBJECTIVES. The expected results of this program
are:
a. A factory at a new institution will be activated in a
timely, cost-efficient manner.
b. The Planning, Research and Activation Branch (PRA) will
coordinate design and construction activities with other Bureau
components.
c. Factory designs will comply with accessibility standards
outlined in the Uniform Federal Accessibility Standards (UFAS)
and with requirements of the most current edition of the Life
Safety Code requirements for Industrial Occupancies. In
addition, the designs will comply with Bureau policy on locked
doors in a means of egress and property protection.
PS 8041.03
12/11/97
Page 2
d. Modifications to FPI standard designs will be identified
and made as early as possible.
e. Each contractor will maintain separate cost and billing
schedules for FPI construction.
f. An activation plan for each location will be developed,
implemented, tracked, and revised as necessary.
g. A Business Plan will be developed whenever a significant
operational change is recommended.
h. Each activation will be evaluated six to nine months after
the new factory is operational.
i. A deactivation plan will be created to ensure the cost
effective deactivation of a FPI plant.
History
PS 8041.03 dated 1997-12-11
Provenance
- Source
- bop.gov
- Retrieved
- 2026-09-20
- Edition
- bop-ps-2026-09-20
- Content hash
95b6a1242745d62241ea9aed554e0851bf54c2a7dd2c0c9f518573fd1882fde4
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.