a. Public Works Projects

(1) The Warden of the institution or the Community

Corrections Manager (CCM) will advise the local community of the

project. (The institution's Community Relations Board may be one

method of informing the community of such projects.)

(2) The Warden must ensure that a National Interagency

Agreement (Attachment A) has been executed by the Bureau and Host

Agency.

(3) The Project Coordinator must prepare the Request for

Public Works and Community Service Projects Approval

(Attachment B). Both the Warden and the Regional Counsel must

approve the form prior to submitting it to the Regional Director.

Normally, the Regional Director is to respond to the Warden

PS 5250.02

10/2/2000

Page 10

within 30 days. If approved, a copy of the request is forwarded

to the Assistant Director, Industries, Education and Vocational

Training (IE&VT).

(4) Upon Regional Director approval of BP-sxxx, the Warden

or CCM will implement the local letter of agreement with the host

agency and forward a signed copy to the Regional Counsel and the

Assistant Director, IE&VT. (Sample wording for a local letter of

agreement can be found in Attachment C. Additional restrictions

may be added to this agreement to reflect the needs of that

particular project.)

b. Community Service Projects

(1) The Warden of the institution or the Community

Corrections Manager (CCM) will advise the local community of the

project. (The institution’s Community Relations Board may be one

method of informing the community of such projects.)

(2) The Project Coordinator must prepare the Request for

Public Works and Community Service Projects Approval

(Attachment B). The form must be approved by the Warden, the

Regional Counsel, and the Regional Education Administrator if the

project is part of an OEP, prior to submitting to the Regional

Director. The Regional Director will ordinarily respond to the

Warden within 30 days. If approved, a copy of the request will

be forwarded to the Assistant Director, IE&VT.

COMPARISON CHART OF PROJECTS

PUBLIC WORKS PROJECT COMMUNITY SERVICE PROJECT

regular paid work detail non-paid work detail/voluntary

program

on-site or off-site on-site or off-site

federal agencies only local gov’t or non-profit,

charitable organizations

national agreement no national agreement required

local agreement no local agreement required

request to regional director request to regional director

long term/short term short term

PS 5250.02

10/2/2000

Page 11

History

PS 5250.02 dated 2000-10-02

Provenance

Source
bop.gov
Retrieved
2026-09-20
Edition
bop-ps-2026-09-20
Content hash
ca0f4ac7c706bfd66744f60998be79e125dac74a66152ea2a9046e2bf75be2fb
View the official source →

The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.

Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.

Coverage · API docs

Bindinglaw

Point-in-time US law with the receipt attached. Source URL, retrieval time, content hash, and validity dates on every answer.

curl api.binding.law/v1/law/coverage

© 2026 binding.law · a Jubal, Inc. productAttorneys and firms never pay. Ever.