WORK ORDERS GREATER THAN $ 25,000
a. General. Work orders greater than $25,000 include the total cost to complete all tasks
associated with a work order. All work orders greater than $25,000 must first be approved by the
Chief, FMB, through the Regional Facilities Administrator.
The Facilities Manager provides the following information for each new submission:
■ Description of the proposed work order, including the size, scope, and any unusual
conditions.
■ Detailed cost estimate.
■ Estimated employee man-hours.
■ Drawings, if required.
■ Projected start and completion dates.
History
PS 4200.13 dated 2026-05-07
Provenance
- Source
- bop.gov
- Retrieved
- 2026-09-20
- Edition
- bop-ps-2026-09-20
- Content hash
f4f72ac0800feae9227338dc6d893c0a7528184a21aacdd73519598aec121007
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.