CMS Pub. 100-06, ch. 3, § 200.2.2

Recoupment After the Initial Demand: When Does it Begin?

activein force · 2026-08-25 – presentas-observed

Timeframe Medicare Contractor Provider

Day 1 Send demand letter. Receives notification by first class

mail of overpayment determination.

(The letter date is the determination

date).

Day 1-15 Process rebuttal

requests received

before or by day

15 deadline. No

recoupment occurs.

Can submit a rebuttal request within

15 days from the date on the demand

letter. (The letter date is the

determination date). Can request an

Immediate recoupment

Day 16-30

Process rebuttal

requests received

before or by day 15.

Performs administrative

activity (i.e., validating

Redeterminations and

updating account

receivables to the

Redetermination

status).

No recoupment occurs

unless the provider

requested the

Immediate

Recoupment

Can request a redetermination and

potentially prevent any recoupment

from occurring on day 41.

Day 31-40 Performs administrative

activity (i.e. validating

Redeterminations and

updating account

receivables to the

Redetermination

status).

No recoupment occurs

unless the provider

requested the

Immediate

Recoupment.

Can request a redetermination and

potentially prevent any recoupment

from occurring.

Day 41 Recoupment begins on

overpayments without a

validate

redetermination

request.

Can request a redetermination and

potentially stop recoupment from

continuing.

1. Recoupment shall proceed on day 41 (with the exception of

immediate recoupment) from the initial demand letter without a

timely and valid request for a redetermination.

2. To prevent recoupment from occurring on day 41, the

provider must file the request for a redetermination no later than

the 30th calendar day following the date of the initial demand

letter.

3. Contractors shall refer to Publication 100-04 Medicare

Claims Processing Manual, Chapter 29, and Appeals of Claims

Decision, to determine what constitutes a valid request for a

redetermination.

4. Contractors shall have internal controls in place to ensure

when a provider is in an immediate recoupment status

the recoupment process continues unless a request from the

provider is received to stop the immediate recoupment.

5. Contractors shall continue to stop recoupment on or after

day 41 from the demand letter date when the appeal request is

received and validated with an outstanding balance.

• Providers have 120 days after the date of receipt of the initial

determination (the notice of initial determination is presumed

to be received 5 days after the date of the notice unless there is

evidence to the contrary) to request a redetermination in

accordance with Publication 100.04, Chapter 29

History

(Rev. 311, Issued: 02-22-19, Effective: 10-07-19, Implementation: 10-07-19)

Provenance

Source
cms.gov
Retrieved
2026-08-25
Edition
iom-2026-08-25
Content hash
797ee8a5efb673572a5c311969a626555c1d49c8b82035b4a027b98fa5b69a41
View the official source →

The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.

Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.

Coverage · API docs

Bindinglaw

Point-in-time US law with the receipt attached. Source URL, retrieval time, content hash, and validity dates on every answer.

curl api.binding.law/v1/law/coverage

© 2026 binding.law · a Jubal, Inc. productAttorneys and firms never pay. Ever.