Required Conditions Other Than Error
If the guidance has been determined to be erroneous, and if adjudication of the matter is
not barred by issues of the timeliness of the request, of ripeness, of sufficiency of
information, or of mootness, then the contractor shall complete a penalty waiver
determination by making separate determinations on each of the remaining required
conditions specified in §§10.2.2 through 10.2.8. The contractor shall make findings on
each such condition, notwithstanding that a particular condition was not met.
History
(Rev. 739, Issued: 11-01-05, Effective: 07-24-03, Implementation: 01-19-06)
Provenance
- Source
- cms.gov
- Retrieved
- 2026-08-25
- Edition
- iom-2026-08-25
- Content hash
2814314f879d4e4fd837bea9968c51fd27c4b8a6ab4b9465eb6975ebfa3029f4
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.