Construction Negligence— Requisite Control

activein force · 2026-08-19 – presentas-observed

A party is deemed to retain some control over the work if there is any part of the work that a

[subcontractor] [contractor] [other] is not entirely free to do in [his] [her] [its] own way.

Provenance

Source
illinoiscourts.gov
Retrieved
2026-08-20
Edition
2026-08-19
Content hash
9f9b5fc433125bc254d91fc0d84d94f4050651a7b816a0c0bc4134ebcb6c20d6
View the official source →

The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.

Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.

Coverage · API docs

Bindinglaw

Point-in-time US law with the receipt attached. Source URL, retrieval time, content hash, and validity dates on every answer.

curl api.binding.law/v1/law/coverage

© 2026 binding.law · a Jubal, Inc. productAttorneys and firms never pay. Ever.