Contractor’s Damages for Breach of Construction

activein force · 2025-01-01 – presentcompiled-edition

Contract—Change Orders/Extra Work

[Name of plaintiff] contends that [name of defendant] increased or changed

the scope of the [project/ describe construction project, e.g., apartment

building] beyond what was required by the parties’ contract. If you find

that [name of plaintiff] is entitled to compensation for this extra work,

you may award damages to [name of plaintiff] based on [the agreed price

provided in the parties’ contract for/the reasonable value of] the extra

work.

New December 2010

Provenance

Source
courts.ca.gov
Retrieved
2026-08-20
Edition
caci-2025
Content hash
9a76663a25efa6fdc62d8fe0d03e5c2f9d862349b02d5aff5beaa8329cfeaf60
View the official source →

The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.

Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.

Coverage · API docs

Bindinglaw

Point-in-time US law with the receipt attached. Source URL, retrieval time, content hash, and validity dates on every answer.

curl api.binding.law/v1/law/coverage

© 2026 binding.law · a Jubal, Inc. productAttorneys and firms never pay. Ever.