CACI No. 4532
Owner’s Damages for Breach of Construction
Contract—Liquidated Damages Under Contract for Delay
[Name of plaintiff] claims that [name of defendant] breached the parties’
contract by failing to [substantially] complete the [project/ describe
construction project, e.g., apartment building] by the completion date
required by the contract. If you find that [name of plaintiff] has proven
this claim, the parties’ contract calls for damages in the amount of
$ for each day between [insert contract completion date] and the
date on which the project was [substantially] completed. Y ou will be
asked to find the date on which the project was [substantially]
completed. I will then calculate the amount of damages.
[If you find that [name of plaintiff] granted or should have granted time
extensions to [name of defendant], you will be asked to find the number of
days of the time extension and add these days to the completion date set
forth in the contract. I will then calculate [name of plaintiff]’s total
damages.]
New December 2010; Revised December 2011
Provenance
- Source
- courts.ca.gov
- Retrieved
- 2026-08-20
- Edition
- caci-2025
- Content hash
968eb4594b0dae4029e8f2348ab672290d09ea84a2002031345bce570e0f5b22
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.