CACI No. 4524
Contractor’s Claim for Compensation Due Under
Contract—Substantial Performance
[Name of defendant] claims that [name of plaintiff] did not fully perform
all of the things that [he/she/ nonbinary pronoun/it] was required to do
under the [terms of the contract/plans and specifications], and therefore
[name of defendant] did not have to [specify owner’ s obligations under the
contract, e.g., pay the contract balance]. [Name of plaintiff] claims that [he/
she/nonbinary pronoun/it] did substantially all of the things required of
[him/her/nonbinary pronoun/it] under the contract.
To succeed, [name of plaintiff] must prove all of the following:
1. That [name of plaintiff] made a good-faith effort to comply with
the terms of the contract and did not willfully depart from them;
2. That [name of plaintiff] did not omit any essential requirement in
the contract; and
3. That the [name of defendant] received essentially what the contract
called for because [name of plaintiff]’s failures, if any, were so
trivial that they could have been easily fixed.
If you find that [name of plaintiff] substantially performed the contract,
the cost of completing unfinished work must be deducted from the
contract price.
New December 2010
Provenance
- Source
- courts.ca.gov
- Retrieved
- 2026-08-20
- Edition
- caci-2025
- Content hash
9338564ea35236534653e461e69d3d75bdd0ccb5febb250bb41432d0ae5d067e
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.