CACI No. 4523
Contractor’s Claim for Additional
Compensation—Abandonment of Contract
The contract between the parties provided for certain procedures to be
followed if [name of plaintiff] wanted to be paid for changed or additional
work that was not initially required by the contract. These procedures
are called “change-order requirements.”
[Name of plaintiff] claims that [name of defendant] required many changes
and that the parties consistently ignored the contract’s change-order
requirements. Therefore, [name of plaintiff] claims that the contract was
abandoned and that the change-order requirements no longer applied.
To establish this claim, [name of plaintiff] must prove the following:
1. That the parties through their conduct consistently disregarded
the contract’s change-order requirements; and
2. That the scope of work under the original contract had been
altered by the changes so much that the final project was
significantly different from the original project.
New December 2010
Provenance
- Source
- courts.ca.gov
- Retrieved
- 2026-08-20
- Edition
- caci-2023
- Content hash
4351ac4f180d3803718ea55a0d090e3cebb7f965fe41c19490360bc34546d974
The link goes to the issuing authority’s own document — the one we read to produce this record. Where a source publishes whole titles rather than sections, your browser may need a moment to jump to the provision.
Unofficial copy of government-published law, reproduced from official sources with full provenance. Not an official publication; verify against official sources before relying on it in a filing. Records in the 'guidance' corpus, and only that corpus, are sub-regulatory (interpretive guidelines, survey procedures) and are not binding law. Validity bounds follow each jurisdiction's declared temporalBasis.